Total work to be done is:
(30 men)(35 days) = 1050 man-days

After 10 days of work with 30 men:
30 men (10 days) = 300 man-days are complete

This leaves 1050 - 300 = 750 man-days left to finish

Now with only 25 men:
750 man-days/25 men = 30 days

So it will take the remaining workers 30 days to finish the job.

Feb 26, 2018

The remaining men will finish the job in 30 days.

Explanation:

The whole job can be unit 1, which can be done by 30 men in 35 days. So a man one day can finish 1/(35*30) job.
After 10 days, the remaining job is 1-10/35 = 5/7.
So every day the remaining 30-5=25 men can finish the job 25*1/(35*30) = 1/42; they still need 5/7/(1/42) = 30 days to finish the job.

Feb 26, 2018

30 days

Explanation:

30*35=1050 => man days required to do the job

30*10=300 => man days completed in 10 days

1050-300=750 => man days of work remaining

25 men to do 750 man days:

750/25 = 30 => days for 25 men to complete the job